6/16/2009
Drywall in the north addition is complete and the painter should start in this area next week. Asbestos abatement is complete and demolition is taking place in the south wing of the existing building. The north addition is now at the same level of completion as the existing north wing. The west addition is ready for drywall. The south addition is framed and plumbing, HVAC and electrical rough-in is underway. The east addition is ready for steel which should be next week. The bus loop curb and gutter and the north drain pan have been poured. Prep work is underway for the play area and the sidewalks.

|
|
|
|
|
|
|