Slab for the west addition has been poured.  Steel for the west and north additions is being set.  The north addition slab is ready to be poured.  Mechanical demolition in the north wing is in progress.  Stem walls for the south addition were poured on Thursday.  Underground plumbing rough-in is starting.

Slab for the west addition has been poured.  Steel for the west and north additions is being set.  The north addition slab is ready to be poured.