Project Partners Public Access > Rangely Public Schools > Rangely High School > Posts > Track replacement looking good!
|
8/5/2009
Base layers down on track. Striping next. Stay off for another week. Working on fire alarm. Started some landscape repairs. Circulation desk. Paint touch up. Last of carpet. Exterior wall repaired. Test & Balancing. Crack seal on asphalt done today. Door hardware starting
|
|
|
|
|
|
|